Discrepancy on % completed & Total Float

2 replies [Last post]
Thomas Ong
User offline. Last seen 19 years 7 weeks ago. Offline
Joined: 21 Oct 2003
Posts: 4
Groups: GPC Malaysia
Planners,
The Percentage complete & total float column on the summary band always change especialy when I sumarise all the activities to its required band. Even I press "schedule", the percentage complete become correct, but sometime I print the report out, the % completed & total float show different.
Anybody can solve this problem?

Replies

Vincent Tham
User offline. Last seen 17 years 32 weeks ago. Offline
Joined: 20 Apr 2002
Posts: 7
Groups: GPC Malaysia
By solved this problems, i recommended you to execute "re-organize now" command 2 times before every time when you want to explain. sure it will solve your problems.

Sure you have any prolems,you can direct contact me. 012-2867713.
MK TSE
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Both PCT and TF of summary bar are determined by various factors which can be control in Option - summarization.
However, settings may be overrided by parameter in each report template. Please check.
Further, to reduce the changing of these 2 value on screen during editing, stop the auto-scheduling function, hope help.