Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

BASELINE DATES

5 replies [Last post]
Prosper Kalabar
User offline. Last seen 4 years 5 weeks ago. Offline
Joined: 10 Apr 2018
Posts: 4
Groups: None

Gents, I need your help.

I noticed that some of the activities in my schedule displays baseline dates that are not corresponding to their dates in the baseline schedule.

 Not all the activities, just some few. 

How you I solve this issue?

Thanks for your help.

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

NO if you have not maintained or assigned a baseline then how in the world can you expect information from that schedule  ?

Prosper Kalabar
User offline. Last seen 4 years 5 weeks ago. Offline
Joined: 10 Apr 2018
Posts: 4
Groups: None

Thanks Gareth. 

Have checked. the early stat and early finish both align with the start and finish dates respectively

Gareth Jones
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 15 Feb 2020
Posts: 2
Groups: None

Hi On your baseline check that the your planned dates and Early dates align.

Gareth

Prosper Kalabar
User offline. Last seen 4 years 5 weeks ago. Offline
Joined: 10 Apr 2018
Posts: 4
Groups: None

Thanks for your response. 

haven't maintained/ asigned BL yet.

But then since I haven't, the current schedule start & finsh dates should display as the baseline start/ finish dates as well. But some activities (not all) are displaying dates displaying BL dates different from the schedule date.

Am using BL Project Start & BL Project Finish to display the information

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

have you sleected maintain baseline ?

have you selected assign basline ?

what columns are you using to display the baseline dates ?

what is your earned value calculation set to ?