Programme Forecast

4 replies [Last post]
Debosky Wale
User offline. Last seen 3 years 43 weeks ago. Offline
Joined: 18 Jul 2014
Posts: 16
Groups: None

 I have been asked as a client-planner to produce an impact analysis in the graphical form of a delay which has been raised by contractor accepted by the client. Apparently what comes to mind is an S curve to forecast new completion date considering contractor usually submit xer file. Just want to clarify if anyone has done this before using any other method as against the aforementioned 

Replies

Mike Testro
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Debosky

When you add progress to a programme you set data date with a dropline that sets the date of the progress report.

The drop line can be Zig Zag or straight.

When the progress is added and the dropline is straight then the actual completion date is revealed when rescheduled

You can set up 2 colums that shows planned completion and actual completion.

This data can then be extracted to a spreadsheet and you can create youe s-curve.

I trust that is clear enough.

Best regards

Mike Testro

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

an S-curve typically deals with resources. I think that the client is looking for a TIA time impact analysis which meands adding the delay into the schedule and showing the activities and logic that was added to impacted the schedule in a graphical Gantt chart or time scaled logic diagram.

Debosky Wale
User offline. Last seen 3 years 43 weeks ago. Offline
Joined: 18 Jul 2014
Posts: 16
Groups: None

Hello Mike,

Thank you so much for your help.

To be honest, I don't understand what you meant, can you please elaborate more, please ?

 

Regards,

Mike Testro
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Debosky The usual and simplest way is to set the dropline to vertical and re schedule. Best regards Mike Testro