Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Possession calender's without possession calender's

7 replies [Last post]
Philip James
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None

Hi

 

Due to policy, our contractor can not create custom calenders. However, due to the nature of the worksite (railway), activities can only occur on certain days. 

So my question is. How do you create a programme with correct total float. As using a 7 day calender for an activity that can only occur for example, every 4th weekend give a false float number

They have create a number of milestones for the 'key weekends' SS with the activity. However if you update the programme, you need to then link to the 'next week' should the work not have finished

 

Hope that makes sense

Replies

Rafael Davila
User offline. Last seen 2 hours 20 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

The incorrect utilization of lags is considered as the principal reason for generated errors when using multi-calendars. It is important to distinguish between two types of lags:

https://mosaicprojects.com.au/PDF/Chronographic_diagramming_method.pdf

  • 1. Lags that presents some technical constraints, such as concrete curing, and always use a continuous working period calendar. These lags should not be affected by non-working days.
  • 2. Lags used as a replacement for an imposed quantity of workload, before the start or the finish of the successors activities. These lags are actually simulated with partial start or finish dependencies. These simulations are insufficient to ensure an accurate calculation of the schedule and could possibly generate wrong answers.

Spider Project solves this issue by providing time lag, volume lag and double lags.  

  • 1. Time lag along with individual lag calendars solves the issue of continuous working periods. 
  • 2. Volume lag solves the issue of an imposed quantity of work.  There is no need to simulate volume lag with partial start or finish dependencies.
  • 3. Start-Start plus Finish-Finish with lags usually is sufficient but if activity execution is non-linear (due to variable productivity and different non-working time of connected activities) intermediate double lags solve potential problems.  
  • 4. Double links solve the issue of partial start or finish dependencies.  The partial start or finish dependencies can be of the type Time Lag or Volume Lag.
Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

excellent idea Paul 

Paul Harris
User offline. Last seen 1 year 5 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

I agree with the previouse comments, change the policy. If you are using P6 then allow the contractor to create a Project Calendar. Another option is to create and assign a rresource with a possesion calendar.

Regards

Paul E Harris

Paul Harris
User offline. Last seen 1 year 5 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

I agree with the previouse comments, change the policy. If you are using P6 then allow the contractor to create a Project Calendar. Another option is to create and assign a rresource with a possesion calendar.

Regards

Paul E Harris

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

 You need to talk to whom ever created the policy of not being able to use custom calendars and find out what the reasoning is. This is one of the benefits of using a scheduling program is that you CAN define your working calendars and have multiple calendars. I don't understand why you think that creating a load of milestones can solve your problem the issue is remains the same whether there are milestones or not. You might as well as use a calendar hanging on a wall and put X marks on the day that you can work. If you can not plan your schedule to shows the planned working days your schedule will never be correct. You may as well NOT track the civil work and just add milestones but the problem is that there will be NOTHING driving those milestones. If the civil work is actually on the critical path and you can not accurately reflect that in your plan then it will never show critical.

Philip James
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None

Hi Mike

Lets assume that chaging policy is not an option, and neither is using some other software

What other ideas are there? 

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Philip

Any planning software worthy of the name can create such a calendar. (Although P6 may struggle)

The contractor had better change his policy amd his software.

Best regards