Hi
Due to policy, our contractor can not create custom calenders. However, due to the nature of the worksite (railway), activities can only occur on certain days.
So my question is. How do you create a programme with correct total float. As using a 7 day calender for an activity that can only occur for example, every 4th weekend give a false float number
They have create a number of milestones for the 'key weekends' SS with the activity. However if you update the programme, you need to then link to the 'next week' should the work not have finished
Hope that makes sense