Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Concurrent Delays in the Schedule

2 replies [Last post]
Dimple Dean
User offline. Last seen 6 years 38 weeks ago. Offline
Joined: 20 Oct 2015
Posts: 18
Groups: None
Hi All, Just asking on this situation regarding concurrency.Contractor's Delay from 30 Oct 2016 to 30 April 2017.Client's Delay from 30 Jun 2016 to 30 Mar 2017.Is it a concurrent delay? many thanks!

Replies

Zoltan Palffy
User offline. Last seen 4 days 3 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Contractor's Delay from 30 Oct 2016 to 30 April 2017

Client's Delay from 30 Jun 2016 to 30 Mar 2017.

Is it a concurrent delay?

if you hand draw this on paper it will be crystal clear  There are 2 parts attributal to the contractor delays. The Contractor Delay #1 is from June 30, 2016 to October 29,2016. The concurrent portion of the delay is from October 30, 2016 to March 30, 2017. The Contractor Delay #2 is from April 1, 2017 to April 30, 2017
Jithin Kambhikanam
User offline. Last seen 1 week 12 hours ago. Offline

Hi Dimple,

Ya it is Concurrent delay.

 

So you can apply LD for a Duration of Contractor Finish Date - Client Delay Impact Date = 30 April 17 - 30 Mar 17 = 30 Days.

 

Mike would be able to answer it much better.

 

Regards

Jithin