Remaining Units on Manual Resource Curve

1 reply [Last post]
Helen Ward
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 20 Apr 2016
Posts: 6
Groups: None
Activity 4 weeks in duration, duration % complete, 100 Planned Units added as resource manual curve over the 4 weeks as 50 20 20 10. Activity started on Baseline Start date, Exoected Finish applied as per Baseline Finish. Data date moved on a week. Past period performance stored. 25% progress seen on activity. First week of Actual Period Units has 50 hours stored as expected. Remaining Units though now read 28 13 8. Why don't they read 20 20 10 as per the Planned Units please? Can't find any help anywhere that's tells me how these Remaining Units have been calculated. Any help appreciated. Using P6 version 8.3.2.

Replies

Zoltan Palffy
User offline. Last seen 7 weeks 7 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that your duration type is fixed duration and units/time