Compensation Events

1 reply [Last post]
James Parker
User offline. Last seen 6 years 36 weeks ago. Offline
Joined: 10 Oct 2012
Posts: 4
Groups: None

Hi all

 

Apologies if this has aready been asked / answered.

Can anyone guide me in the best direction on how to schedule compensation events into the project baseline? Im working under the NEC contract.

Thanks 

James

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi James

It is the same method as described in an Impacted as Planned delay analysis method.

1. Calculate the duration of the compensation event.

2. Set this into a Sub Chart.

3. Link to the affected task(s).

4. Hit F9 and wait for the howls of protest from the CA.

Best regards

Mike Testro