Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Progressing a Schedule Before Baselining

3 replies [Last post]
Jordan Thomas
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 2 Mar 2015
Posts: 3
Groups: None

Hello,

After building the project schedule, but before reaching an agreed-to baseline with the client, is it ok to enter progress dates into activities that have taken place in the time between putting the schedule together and reaching the agreed-upon baseline with the client? Or is there a different standard method for doing this?

Replies

Raymund de Laza
User offline. Last seen 31 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762
The idea is that the baseline shall be scheduled as current status but not statused as actual. Meaning the schedule is planned as current status. Once accepted as baseline then create a copy to update and statuses the activities accordingly.
Mike Testro
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jordan

I take the opposite view to Patrick.

The progress data should reflect what actually happened so it should be added to your "trial" programme.

If changes are required to get approval then the new programme is easily progressed a second time.

Best regards

Mike Testro

Patrick Weaver
User offline. Last seen 4 days 7 hours ago. Offline
Joined: 18 Jan 2001
Posts: 373
Groups: None

Not a good idea - the baseline may be adjusted to reflect what is actually happening but generally the 'baseline' is the planned situation.