Hi Everyone,
Could you please shed more lights on the essence of throwing-in lots of constraints in a schedule. I am reviewing a schedule where around 15 Finish ON/Before, Start On, Finish On/After constraints exist.
Most amazing to me, most of this constraints are used under WBS- Control Milestones EVEN THOUGH the end dates of the related activities doesn't correspond to the control milestone. Below are few illustrations:
Control Milestones:
1. Mock Up Finish - 15/10/15 (Finish ON/Before
2. Building 1 Finish - 20/11/15 (Finish ON/Before)
3. Building 2 Finish - 20/12/15 (Finish ON/Before)
3. Building 3 Finish - 20/01/16 (Finish ON/Before)
4. Soft Landscaping- 30/05/16 (Finish On/After)
5. Project Finish- 30/06/16 (Finish On)
Last Activity Finish (Actual Finish)
1. Mock Up Finish - 15/09/15
2. Building 1 Finish - 10/10/15
3. Building 2 Finish - 15/11/15
3. Building 3 Finish - 20/12/15
4. Soft Landscaping- 30/05/16
5. Project Finish- 30/06/16
NB-
a. The control milestones are linked to FS to snagging activities
b. the works are not even planned to finish at the scheduled control milestoes.
Awaiting comments from our experts.
Replies