construction civil works productivity rates

1 reply [Last post]
hany esmael
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 5 Mar 2008
Posts: 28

Hi Everyone, I would like to share with you construction civil works productivity rates, I found this file very useful, what you think?

Productivity Rates for Tilling    
      
Size. (Cms)LocationAreaManpowerProduction RateRemarks
    (Sqm. Per day) 
      
30 X 30FloorKitchen1 Mason, 1 Helper14Residential  Area by Sub-Contractor
30 X 30Floor with patternCorridor1 Helper, 2 Masons10Residential  Area by Sub-Contractor
40 X 40FloorBed room1 Mason, 1 Helper22-25Residential  Area by Sub-Contractor
20 X 20FloorStore (small area)1 Mason, 1 Helper 10Residential  Area by Sub-Contractor
30 X 60FloorBathroom2 Mason, 1 Helper6Residential  Area by Sub-Contractor
30 X 30Floor + WallBathroom2 Mason, 1 Helper5 
10 X 10WallKitchen1 Mason, 1 Helper8-9Residential  Area by Sub-Contractor
30 X 60WallCorridor1 Mason, 1 Helper14-15Residential  Area by Sub-Contractor
30 X 30WallBathroom2 Mason, 1 Helper7Residential  Area by Sub-Contractor
     Residential  Area by Sub-Contractor
Notes:     
1. 1 Day = 10 hrs.     
2. Gang Size:     
    1 Mason + 1 Helper for Kitchen and Bedroom.   
    2 Mason + 1 Helper for Bathroom.    

Replies