Hi Everyone, I would like to share with you construction civil works productivity rates, I found this file very useful, what you think?
Productivity Rates for Tilling | |||||
Size. (Cms) | Location | Area | Manpower | Production Rate | Remarks |
(Sqm. Per day) | |||||
30 X 30 | Floor | Kitchen | 1 Mason, 1 Helper | 14 | Residential Area by Sub-Contractor |
30 X 30 | Floor with pattern | Corridor | 1 Helper, 2 Masons | 10 | Residential Area by Sub-Contractor |
40 X 40 | Floor | Bed room | 1 Mason, 1 Helper | 22-25 | Residential Area by Sub-Contractor |
20 X 20 | Floor | Store (small area) | 1 Mason, 1 Helper | 10 | Residential Area by Sub-Contractor |
30 X 60 | Floor | Bathroom | 2 Mason, 1 Helper | 6 | Residential Area by Sub-Contractor |
30 X 30 | Floor + Wall | Bathroom | 2 Mason, 1 Helper | 5 | |
10 X 10 | Wall | Kitchen | 1 Mason, 1 Helper | 8-9 | Residential Area by Sub-Contractor |
30 X 60 | Wall | Corridor | 1 Mason, 1 Helper | 14-15 | Residential Area by Sub-Contractor |
30 X 30 | Wall | Bathroom | 2 Mason, 1 Helper | 7 | Residential Area by Sub-Contractor |
Residential Area by Sub-Contractor | |||||
Notes: | |||||
1. 1 Day = 10 hrs. | |||||
2. Gang Size: | |||||
1 Mason + 1 Helper for Kitchen and Bedroom. | |||||
2 Mason + 1 Helper for Bathroom. |