Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Imported Material Resources Budget Units & Duration set to zero

1 reply [Last post]
Mohamed El Turky
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 8 May 2013
Posts: 5
Groups: None

Hi Everyone, 

i just imported a programme, i discovered that durations & budget units of material resources are set to zero, any advice ?

Best regards,

Replies

Alain De leon
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 15 Jun 2012
Posts: 18
Groups: None

check your resources if there is price / unit and quantity on the budgeted units