hello - hope someone can help - I am new to primavera planning with P6 and there is something i dont understand and would love some help-
P6 set up : fixed duration units/time - physical % - no resource assigned to any activity
scenario :
I have 3 activities all f-s linked with no constraints -and a DD set to aug 1st
1st activity starts on the 1st and finishes on the 3rd -100 % c/t
2nd activity starts 4th ends 21st - 100% c/t
3rd activity starts 22nd with and end 29th Aug 10% complete
problem:
why does the 3rd activity "snap back" to be in line with activity 1 when I re scedule so it looks as though it starts on the 1st where as I would expected to start on the 22nd and (visually) follow the end of activity 2.
If i make activity 2 99% c/t activity 3 stays where i think it should be -
what am i not doing right -
thanks andy