Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera Project Duration

No replies
Wilfredo Barbacena
User offline. Last seen 8 years 12 weeks ago. Offline
Joined: 13 May 2009
Posts: 30

Hi,

Would like to ask some help with regards to the image below. Have asked a subcontractor to provide an EOT and to use the latest update of the schedule without the baseline. I've noticed that in Primavera 8, the duration of the civil works doesn't seem to tally. Looking at the program that it still uses the original plan dates, allthough there are no baseline. This is only showing to activity with actual dates, is this an anomaly of Pv8 if it's then what are the remedial of this?

Need advice and ragards.

 

1373
p3_jpga.jpg