Generating an Early, Late, & Planned Curve in P6

2 replies [Last post]
Melissa Schiller
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 7 Sep 2010
Posts: 4

In P3, users could produce an Early, Late, & Planned Curve.  P6 doesn't do this. 

I am able to produce an Early & Late Resource curve by copy/pasting the data from the resource assignments view into an excel spreadsheet, but I cannot produce a planned curve.

I am curious to know what others are doing to generate a planned curve from P6 without simply taking the average of the early & late units. 

Replies

Raymund de Laza
User offline. Last seen 32 weeks 3 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Melissa,

The early dates of your Baseline or Initial Schedule represents the Planned.
Use the Baseline to generate the required curve.

mohd mofaz
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 10 Jul 2011
Posts: 3
Groups: None

Go to resource graph on the task bar in P6. Then right click on the graph to customize according to what you want.