In P3, users could produce an Early, Late, & Planned Curve. P6 doesn't do this.
I am able to produce an Early & Late Resource curve by copy/pasting the data from the resource assignments view into an excel spreadsheet, but I cannot produce a planned curve.
I am curious to know what others are doing to generate a planned curve from P6 without simply taking the average of the early & late units.