Fs Links and Critical Path.

Member for

14 years 4 months

Gary,

Thank you I just Found the Thread that Mike Mentioned.I think it has all answers that i wanted.

 

Regards,

Member for

16 years 7 months

AB,

This has been discussed many time s before as Mike says, and the thread he suggests you look at was probably the most in-depth discussion on it

 

Briefly, I think you should use FS(0) relationships wherever possible, but feel there are times when other relationship types are more appropriate -not becuase the plan gets too overcrowded when you split tasks down into smaller elements requried for FS, but because it can sometimes be difficult / impossible to define / measure precisely where the split should be.

I have never found a good reason to use negative lag.

 

Your second point "if We only use FS relationship the it means that all activities will be critical?? " Is quite wrong.

-All activities would only be critical if you had a project whereby every activity only had 1 sucessor and 1 predecessor. This is never the case.

Your comments suggests to me you have never tried to build a schedule using only FS links -I think you would get a much stronger insight as to which approach is better by giving it a go yourself, than merely posting on the forum. I'd certainly suggest trying it out at least once before deciding it was not the best way.

 

 

Cheers,

 

G

Member for

19 years 10 months

Hi AB

My maxim is that every task should have at least 1 predecessor and at least one successor.

Every link should be FS and the only time to use a lead lag is to allow for curing / drying out periods (set to calendar days)

You will find this expressed in many forum in PP - check out the thread on "Ban these planning abominations".

I have no intention in taking part in another similar debate.

Best regards

Mike Testro