Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Can we create relationship in Resouces

1 reply [Last post]
Kumar Baiju
User offline. Last seen 10 years 12 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi to all

Can we give the relation for different resources for any activity as we do in activity.
for example if we assign two different resources 1. Engineer and 2nd Draftmen. can we give the relation so that Draftmen will start work after Engineer work finish.Please guide me

Thanks for support in advance
KBJ

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Primavera can't do that, nor can MS Project. Spider may, and I'm not sure about Asta.

But why don't you just have a seperate activity per resource?

 

Also, please don't post the same question in multiple forums. I have deleted the copies.

 

Cheers,

 

G