Retaind Logic & Override Logic

2 replies [Last post]
Tanveer Ahmad Niazi
User offline. Last seen 6 years 3 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

What is Retained Logic & Override Logic, Some one please explain

Thanx - Tanveer

Replies

Tanveer Ahmad Niazi
User offline. Last seen 6 years 3 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Thanx Amit

cheers

Amit Parmar (PMP)
User offline. Last seen 11 years 30 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

I guess its "Retained Logic" and "Progress Overide" :), the difference between is the way you want Primavera to calculate dates.

say for example Activity A&b have FS relationship but activity A gets delayed and Activity B starts without Activity A finishing, in this case :

1) Retained Logic - would follow logic and hence while scheduling Activity B Remaining ES would be calculated from the EF of Activity A, therefore you might see a break in the dates for Activity B.

2) Progress over ride - This would override logic and schedule both the activities according to the Progress they have achieved. In this case you will not see any break in Activity B.

Hope it helps,

Regards

Amit