In P6: Can only one Resource Type (e.g., Labor and NOT Nonlabor) update the entire Units % complete?

Hi All,

 

I want the actual units of a certain (Labor) Type resource and not the actual units of the combination of resources allocated to the activities to update the UNITS % COMPLETE .  e.g.,  for a given task, i have two types of resources allocated to it, one of type LABOR and the other of the type NONLABOR..my question : can the UNITS % COMPLETE be only updated based on the quantities of the LABOR type only resource?

 

Thanks a bunch

 

Moe

K
Khaja Sharief 👤 Member for 17 years 9 months

P6 considers only labour & non labour units for deriving units % complete and will not consider material units for calculating percentage complete.

The calculation of Activity % Complete = Units % Complete = (Actual Labor Units + Actual Nonlabor Units) ¸ (Actual Labor Units + Actual Nonlabor Units +Remaining Labor Units + Remaining Nonlabor Units).

If multiple resources have been assigned to the activity it would be sum of all labor and nonlabor units.

Forum Sponsor

Top Posters

Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts