Using P 6.2.1, I want to import into the WBS table via excel (to save typing). Anyone know how to do this?  Thanks, Mark

Replies

mimoune djouallah
User offline. Last seen 1 week 5 days ago. Offline
Joined: 14 Oct 2006
Posts: 387

Mark

 

ok a little late, i have made a guide how to import a wbs iinto Primavera P6, either using the sdk or the xer parser.

the process is rather time consuming but it give a good idea how the database treat the wbs structure.

http://www.plannertuts.com/uncategorized/using-primaveras-xer-file-parse...

 

hope this help.

regards

mimoune

jeoffrey reyes
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 214

Hi Mark,

 

You can use also SDK.

Cheers,

Mark Dunn
User offline. Last seen 6 years 29 weeks ago. Offline
Joined: 14 Sep 2010
Posts: 8
Groups: None

Thanks guys.

Arend Kok
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 19 May 2008
Posts: 38

The .xer file parser is another usefull way to do this.

Richard Rush
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 1 Jan 2004
Posts: 31
Groups: None

Mark,

 

2 methods :-

 

Excel to Project.xls to P3.1 to P6

or Excel to MS Project (Outlining defines the WBS tree) to P6

 

Best Regards