Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

rate of progress

3 replies [Last post]
Stephen Briggs
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 9
Groups: None
Hi guys

Does anyone have any sensible statistics on the tail-end of progress curves? What I’m looking for is typical rates of drop-off in progress such as ’the last 10% of a construction project takes 25% of the overall duration’ or something similar. What are your experiences?

Replies

Gary Whitehead
User offline. Last seen 6 years 8 weeks ago. Offline
Stephen,

It’s very hard to make a generalisation of this nature:
-The %age weighting used to define the ’last 10%’ will usually be a factor of cost to the contractor, or just labour resources.
-The tail end of the project will usually consist of commissioning and snagging. Commissioning requires no (or at least minimal) plant or materials, and little contractor labour, hence it often has a low %age weighting compared to the importance and duration. Snagging often carries no weighting at all since it’s work that should have been done right first time.
-But how long the commissioning & snagging will take as a %age of overall duration depends entirely on the project. It could be a 12 month project with 3 month’s commissioning, it could be a 5 year project with numerous sectional completions meaning the final section’s commissioning is only a month. It could be a process job where commissioning includes a 3 month proving period, it could be a single-story car park where commissioning is little more than checking the lights work.

Cheers,

G
Basir Ahmed
User offline. Last seen 15 years 39 weeks ago. Offline
Joined: 24 Feb 2009
Posts: 14
Tail end of the project :

Are you refering to the last horizontal section of the S-Curve? if yes then they are not always as they are seen on the S-Curve. the work usually is dont till the last date and the almost horizontal section is very rarely achieved.


Usually projects, exceeding 3 to 4 months go for running invoices. and if this is the case with your project too then u need not worry abt the last 10%
Anoon Iimos
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
What do you expect with the last 10% of the works?

1. If I am a contractor, and my contract has 10% retention, I’ll see to it, that I can make profits in the first 90% of the works.

2. The last 10% is a gamble - if it can be claimed, then it’s my bonus.

3. If I feel that the customer can still sustain the last 10% to go along to another 90%, then, this would be a different story. I will hire an expert! (of course in contracts!)

What’s a tail-end of progress?

cheers!