Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Floor cycle duration of High rise building

7 replies [Last post]
kier legard
User offline. Last seen 14 years 18 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 96
Groups: None
Hi,

How is the floor cycle duration of high rise building determined?


regards,

kier

Replies

Ben-Al Pasil
User offline. Last seen 9 years 49 weeks ago. Offline
Joined: 16 Feb 2010
Posts: 6

Dear Sirs,

 

can anyone give me sample of high rise building program in Primavera, I dont have much experience in such project.

besides Im a new User in P6. only 2 years. 

 

Thanks!

Santhosh kumar Na...
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 66
Yes i Agree with Arman,

Normally high rise building cycle varies from 7 to 9 days per floor, again depends the availability of tower cranE.
armando moriles
User offline. Last seen 13 years 8 weeks ago. Offline
Joined: 2 Feb 2003
Posts: 66
Groups: None
Kier,

1 mh/sm for table form seemed ok but for beam u may use 2 mh/sm. It is already a fast rate...

Tower crane availability highly dictates cycle time especially if MEPF, Architectural and balance of your structural works are already progressing in parallel. So you have to make sure that your intended cycle time goes along with the total tower crane hours availability.

Regards,

Arman
kier legard
User offline. Last seen 14 years 18 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 96
Groups: None
Hi Arman,

Thanks a lot for the info,

Please confirm if my productivity rate for formworks are correct.

table forms for beam and slab =1mhr/sm
Wall and column forms= 2 mhr/sm

Does anybody know how crane analysis is done.Do I have to consider the load of tower crane for 1 floor.Does the cycle time dictates the number of tower crane?

Regards,

kier

armando moriles
User offline. Last seen 13 years 8 weeks ago. Offline
Joined: 2 Feb 2003
Posts: 66
Groups: None
Kier,

I would like to suggest the following:

considerations:
1. Podium level not included;
2. 2 to 3 sets table and beams forms;
3. 2 sets column and shear wall forms;
4. 1 to 2 sets re-shoring;
5. Slab design with beams (not flat slab);
6. 1 Tower Crane;
7. 1 to 2 units man lift (fast car);

Working hours:

Structural Workers: 7:00 start
MEPF Workers: 7:30 start

cycle time:

7 to 9 days per floor (slab with beams)
5 to 6 days per floor (flat slab)

notes:

1. The number and type of form sets highly dictates the speed of structural construction per floor. It is very important to know what is being considered in the tender programme as it is expensive.
2. Other factors that have to be considered:
2.1 Materials and Manpower Movement;
2.2 Tower Crane Analysis;
2.3 Construction Lifts Analysis;
3. Discuss with Forms and Scaffolding teams or supplier regarding rates of progress.
4. Wet weather


I hope that the above may make sense to you. I also hope that others may contribute or comment.

Best regards,

Arman
Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Kier,

You need to determine the method of construction of the vertical elements and the slabs.

Usually for high rise you have self-climbing formwork like the one from Doka. See link

http://www.doka.com/doka/en_global/whatsnew/news/pages/05631/index.php

Subsequently, you can determine the floor cycle.

Best,

Samer
Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
it can be determined by making a plan or schedule.