Short Term Programme

4 replies [Last post]
James Young
User offline. Last seen 12 years 50 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 71
Groups: None
This may seem a bit silly, but how much information do i need to include within a short term weekly Programme?

Thanks,

J

Replies

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi James

Start PowerProject Help

Type in Time Slice and list topics

Go to nr 9 on the list and follow the instructions.

Best regards

Mike Testro
James Young
User offline. Last seen 12 years 50 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 71
Groups: None
How do i do a Time Slice Filter?

Regards,

James
smiling shagger
User offline. Last seen 15 years 36 weeks ago. Offline
Joined: 29 Mar 2006
Posts: 24
Groups: None
in nepal, probably theres no need of short term program, we solve any lookahead/recovery by everybody project participants sitting down together over a pot of bonk

hempfully,
smilingshagger cum global backpacker
Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi James

Just do a time slice filter on your main programme from week before - current week - next week and your short term programee will appear.

You may need to do sub filters for each work package.

Best regards

Mike Testro