Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Slipform Productivity Rates

3 replies [Last post]
Ismail Vandeliwala
User offline. Last seen 12 years 29 weeks ago. Offline
Joined: 11 May 2004
Posts: 23
Groups: None
Can anyone please help me with information regarding slipforming productivity rates.

If i am slipforming a lift core how many mts can i achieve per day (this would include the rebar fixing, shuttering for the boxouts/leaveouts, concreting and Slipping the form). Can i continue the slipforming operation without stoppages that is as continous operation?

In the case that it can be done without stoppages how many days would it take to slipform 115m ?

Replies

Karim Mounir
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Ismail,

We used slipform in construction of silos in the project that I’m currently working in.
Generally, you can operate the slipform 24/7 but you must have enough steel fixers, general labor, concrete finisher, rc concrete, etc..
You should also consider duration for assembly of the slipform.

Karim
Charleston-Joseph...
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi Ismail,

Pick up the phone and ask Sonia of JBR1 or Tara of JBR3 or

Riswan of DIFC Gate Village or

You can also check with Arabtec their whereabouts

Call BRM.

I agree with Vishwas,

There is a limitation on how high Core Wall will go up.

Cheers,

Charlie
Vishwas Bindigana...
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 24 Apr 2004
Posts: 97
Groups: None
Ismail,

Normally in the UAE (for lift cores), it is 3 mts per day. You wouldn’t get an approval from the consultant for anything more than that.

But, then, slipforms have to be coordinated with crane height - which in turn has to be synchronous with the slabs.

Ultimately, the corewall casting depends on the slab-to-slab cycle.

Happy Planning!