MEP

2 replies [Last post]
Pacifico Pallasigui
User offline. Last seen 11 years 47 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
I have here activities for Mechanical ,Electrical & Plumbing installation for our project in russia a multi functional building project.

MECHANICAL & PLUMBING INSTALLATIONS

1. Heating Station
2. Smoke Protection & Ventilation System
3. Heating & Cooling System
4. Heating System Floor Convector
5. Mechanical Vertical shafts
6. PLUMBING - DOMESTIC, COLD & HOT CIRCULATION SYSTEM
7. SPRINKLER AND HOSE REEL SYSTEM
8. DOMESTIC & STORM WATER DRAINAGE SYSTEM
9. BMS SYSTEM
10. COOLING SYSTEM (CHILLERS & DRY-COOLERS ON THE ROOF)

ELECTRICAL INSTALLATIONS

1. ELECTRICAL SUBSTATION
2. EARTHING & LIGHTNING PROTECTION SYSTEMS
3. POWER DISTRIBUTION SYSTEM
4. ELECTRIC LIGHTING SYSTEM
5. RADIO SYSTEM
6. TV SYSTEM
7. CCTV (CLOSED CIRCUIT TELEVISION) SYSTEM
8. FIRE ALARM & PUBLIC ADDRESS SYSTEM
9. CLOCK SYSTEM
10. TELECOMMUNICATION SYSTEM
11. SECURITY SYSTEM


My Questions:

a. What systems or activities are included in TESTING & COMMISSIONING?
b. Around How many months is Testing & Commisioning (Duration)?
c. When is the proper timing or relationship to start Testing & Commisioning?
d. What is the relation of this list activities example: power distribution needed to start some systems.

Can anybody help me because im a civil engineer and have no experience in MEP.

Thanks

Pacifico

Replies

Pacifico Pallasigui
User offline. Last seen 11 years 47 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
Thanks for all the help & tips bro

The project is a two building one is 7 storey bldg and adjacent to that is a 9-storey building and this two buildings is divided by an atrium.

Thanks
pacifico
Pranab Kumar Deb
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
dear Sir,

a.TESTING & COMMISSIONING is rquired for all the system listed above i.e u have to connect all the systems above with an activity name "TESTING & COMMISSIONING" at the end.
b. Depends on the built up area of the building , nos of flooors how much resources u have and all .
c. It can start after the set up for the system has been completed personally i prefer this activity at the end of completion of the set up.
d. Power distribution is needed for all the listed systems.
for a copy of my project u can mail me deb.icd@tajnet.com
i may be late to reply as will move out on vacation
regards
deb