New Austrian Tunneling Method - Productivity Parameters

1 reply [Last post]
Ashish Abraham
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 28 Nov 2006
Posts: 16
Groups: None
Does anyone have any input about productivity numbers for the New Austrian Tunneling Method (NATM)? Any help would be greatly appreciated!

Thanks.

Replies

Paul Harris
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
These would depend on a number of factors such as type of rock, stratification, slope, size and depth of tunnel, water ingress, method of excavation etc.

NATM is a design and construction monitoring methodology not a production based estimating process.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au