Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Effect of wind on Construction work.

2 replies [Last post]
DATTATREYA PADHARTHI
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
I have gathered from Construction Managers (Saudi experience) is that in al-Jubail area 1-2 cumulative days/month are lost due to high speed winds/ Sand Storms during April-May.
Has anyone done analysis on effect of wind on Construction work specially Structural erection/ Piping erection work at high elevations.
What is the effect of the same on productivity at ground level?
Is this normally taken care during planning stage in these areas?

Regards
Dattatreya

Replies

Jihad Daniel
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 7 May 2005
Posts: 99
Groups: None
In Al-Jubail SAFCO project, we have taken in consideration during planning stage the effect of wind on construction. This was agreed with the Engineer/Owner during the clarification meetings in early stage before proceeding with work. It’s the same when you are considering rainy weather conditions in certain areas. You can highlight in curtain the period of April-May and consider in your estimation that the productivity will be reduced by "x" % or consider that in this period we have "y" days to be lost. In our project, we majorated the overall duration of the activities in this period to take into account weather conditions.
It’s very essential that Contractor would know about the ground, site, weather, etc. conditions before getting the job as it’s difficult for him to claim money or time for conditions that he should have known and investigated about. Unless it is an inclement, exceptional, adverse weather conditions such as rarely happened before and unpredictable by weather forecast, the contractor can record these impacted days and attempt to claim extension of time.

Regards,
J. Daniel
Sandeep M
User offline. Last seen 16 years 40 weeks ago. Offline
Joined: 20 Jun 2005
Posts: 5
Groups: None
In a place like Bahrain the wind speeds around the year are in the range of 15 to 20 Knots. The worst hit projects are the offshore projects. During the year 2002 to 2003 we lost 23 working days on our Mega port construction project. No account of this delay was considered in our initial Clause 14 programme.