Problems change effect

3 replies [Last post]
WAEL ELHAJJ
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 55

Dear All, 

I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals. 

the schedule early finish and early end dates seem the same. no effect on succesor activies . 

how can i over come this problem 

Replies

Ronald Winter
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

I am almost afraid to ask but did you re-calculate the schedule?  P6 is not like MS Project in that the default setting is to not automatically re-calculate the schedule after any change.

WAEL ELHAJJ
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 55

ronald ,

i imported a file from P3 

any change to any activity is not affecting the rest of the project .. 

i even changed the data date ... 

nothing happened 

Ronald Winter
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Do you mean the Tool, "Apply Actuals" or "Update Progress" or are your referring to some other process?