Climbing System Formwork

1 reply [Last post]
stevan sarapa
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 7 Jun 2003
Posts: 5
Groups: None
Gentlemen,


We are now near to complete L03 level of typical concrete structure (start was in the basement B04 level). From L03 level (large transfer slab) we have two towers, from L04 to L12 level. Typical level consists of two core walls, columns and suspended slab with beams
(see http://groups.msn.com/stevansarapa/documents.msnw).
I have been asked to do exercise , to compare how faster completion of structure will be achieved by hydraulic climbing formwork for the core wall then in case when we use classic frame formwork for core wall.
Please advice for the production rates for self climbing system.
What can be proposed floor sequence?

Regards,

Stevan

Replies

MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
To my knowledge, there is not much gain on using self-climbing form since the starting level is 3 and climb up to 12 only.
To establish the system, you need to spend sometime, at least 3 weeks. For first 5 levels (min), you need consider those adjustment on self climbing together with learning cycle for worker, then the rest is steady cycle time.
Depend the size of the core, the cycle be from 4 days to 7 days per level.
Further, don’t miss the additional plant for this system form, since it is higher than the normal working level, you have crane and concrete pump (may be) above the top level of system formwork. To set up those equipment, need time and resources.
Finally, consider the slender of the core, may not allow to build too high from the constructed floor slab.