Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Suretrak - Weekdays and Weekend days Count

3 replies [Last post]
k.k. reddy
User offline. Last seen 21 years 10 weeks ago. Offline
Joined: 13 Feb 2003
Posts: 4
Groups: None
I am creating a project schedule with SureTrak,
The following is the issue,
Any help will be appreciated. Thank you.

I want to count weekdays and weekends.
For one item, I put in Start_Date 01/28/03 and 62 days to complete.
End_Date is suppose to be 03/31/03, but SureTrak is giving me
End_Date as 04/23/2003. Is there any way I can count all days,
both weekdays and weekends, and put in End_Date as 03/31/03
on the screen, as calculated.




Replies

Ed van der Tak
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 5 Mar 2002
Posts: 86
Hi,

While checking your question in suretrack I found the following :

1) Check the exceptions option in the calendar, it could contain dates!
2) The global calendar has effect on using calendar no. 1. Make this global calendar "empty" ie 7days/week and define exceptions in the others 1,2,3,4 etc calendars. Only days applicable for ALL calendars should remain in the global calendar.

I hope this solves your problem.

Plan for the best,

Ed van der Tak
ARAM Planning Consultants
The Netherlands
k.k. reddy
User offline. Last seen 21 years 10 weeks ago. Offline
Joined: 13 Feb 2003
Posts: 4
Groups: None
Steven, No luck.
Even I created new calendar, with 7 days 8 hrs day week.
Steven Oliver
User offline. Last seen 11 years 21 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Check your calender, if Sat/Sun are classed as non working, either change them to working days, or create a new calender with the working days you require.

Same goes for holiday days.

have fun