Changing original project start date after most of the project activities are entered in SureTrak 3.0

1 reply [Last post]
Ken Johnston
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 6 Mar 2012
Posts: 2
Groups: None

i have started a new project and the owner wants to change the start date for working day calculation. I want to movethe start date and the activies to an earlier date.

Replies

Daniel Limson
User offline. Last seen 4 years 39 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Ken,

There is actually a way to do it, I am not using Suretrack anymore but I have had that situation before and I believed you need to change the Project Start Date as you open the file (click overview) and you also need to adjust the data date.

Regards,
Daniel