Why can't I open two projects and copy activities from one to the other? pastes into the same...

No replies
John Reeves
User offline. Last seen 22 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Why can't I open two projects and copy activities from one to the other?  the 2nd is just a later update, tries to paste back into the same project... - this should be easy, like from one spreadsheet to another - is there a trick to this?  Pastes it back into the same one and want to just rename the activities....I guess I could export and import but surely there is an easier way....

John Reeves
User offline. Last seen 22 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Wow, fastest answer ever on this site.  Thank you very much.

John Reeves
User offline. Last seen 22 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Wow, fastest answer ever on this site.  Thank you very much.

david kelly
User offline. Last seen 1 day 56 min ago. Offline
Joined: 12 Feb 2016
Posts: 40
Groups: None

Yes there is a trick. Some of this might not be necessary now, but I always:

Group and sort by WBS
Do not 'hide if empty'
Always select using the left mouse button, before right-clicking and paste