Primavera Visualizer Scheduler Compare - can you export it to excel?

1 reply [Last post]
John Reeves
User offline. Last seen 21 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Primavera Visualizer Scheduler Compare - can you export it to excel?  It has gotten better, it is still weird and clunky though - I can only seem to print of the screen.  Can you export to excel, I tried to copy and paste to excel - that did not work too well.

Replies

Rodel Marasigan
User offline. Last seen 12 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Yes you can. Go to Option and select General Tab. Select CSV and select the file destination and file name. Click Save and Draw. Then go to the folder where you save. Double click the csv file and it will open in Excel. See below: P6-Schedule-Comparison