How to modify "Note to ressource" field

4 replies [Last post]
Frederic Fasquelle
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 61

Hi everybody,

my organisation recently moved from P6V7 to P6V19.
We have a concern regarding field "Note to ressource".

On our previous version, we were able to modify or delete content. Now on V19, this field is locked with no possibility to modify it. We can add a comment but it stacks with others.

Does anybody have an anwer on how to solve it?

regards

Replies

Zoltan Palffy
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Clear the checkbox when you finish reading the new feedback so you will be aware of subsequent new feedback.

Frederic Fasquelle
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 61

Hi,

in fact I can't find any parameter in admin part. If anybody have a clue to find it, it would nice

Zoltan Palffy
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

check your admin rights and make sure you have the proper rights to do this.

Alexandre Faulx-B...
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello Frederic,

"Note to resource" allows the planner to write/send short notices to the ressources assigned to this specific activity. the resource then will be able to answer in the right side of the screen. This build some kind of forum where the planner and the resource will discuss the data pertaining to the activity.

In my own opinion, it is more coherent not to be able to delete or edit the notes, in order to keep the forum history alive.

Alexandre