Sort by Project in Activity View

4 replies [Last post]
Al MacLeod
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 22

Hi,

I have several projects that i open at the same time. I want to sort the projects into a specific order. They are shown in the EPS in the order i want. When i open them all and go the activity view they are in a different order. How can i specify a sort order?

Thank you

Al

Replies

Al MacLeod
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 22

Hi All,

I also found that if you get the project in the correct order in the project view using the project ID as the sort then sort the WBS alphabetically in the activity view they go to the same order as the project view.

Thanks

David Kelly
User offline. Last seen 3 years 12 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Sorry, that no longer works. It is OK in the activity window, but not the project window. They have had twnty years to get this right. I shall report back if I find a way to properly order projects in version 19
David Kelly
User offline. Last seen 3 years 12 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

With all the projects open, go to the WBS window, Collapse All, and just move them up and down with CTRL-arrow key.

Thanks Oracle, you changed that keystroke sequence. Took me 20 minutes.

Santosh Bhat
User offline. Last seen 13 weeks 5 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Try making the first row of your grouping as "EPS/WBS" and uncheck the Indent box.