Export XER file with only some activities

5 replies [Last post]
Lyna Bellahsene
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 21 Oct 2019
Posts: 4
Groups: None

Dear all, 

 

I want to export an XER file with only some activities not all of them (i want to use it in schedule analyzer after) any help?

 

Thanks!

Lyna

Replies

Patrick Mullen
User offline. Last seen 5 years 6 weeks ago. Offline
Joined: 15 May 2020
Posts: 19
Groups: None

Hi Lyna, are you trying to compare the changes between specific sections of the schedule, and ignore other sections? What information are you trying to analyze once you get the schedule into SA?

Lyna Bellahsene
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 21 Oct 2019
Posts: 4
Groups: None

ok thanks a lot!!

Lyna Bellahsene
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 21 Oct 2019
Posts: 4
Groups: None

ok thanks a lot!!

Zoltan Palffy
User offline. Last seen 11 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

copy the project

filter for the activities that you DO NOT WANT now you are left with waht you want 

press deleted

file export xer 

remember you can not schedule THIS project as there may be ties to activites that have been deleted

David Kelly
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

You need to copy/paste what you want into a new project, and export that. You can ponly export whole projects