Transfer Progress between 2 Programmes

4 replies [Last post]
Mike planner
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hello All, 

 

I have progresss a programme and added some new activities as Rev 08, progressed as at 14-Feb-20 

However, my previous progress is Rev 07, which was progressed on the 17-Jan-20. 

Can i know if there is a quick method that i can transfer my progress from Rev 08 to Rev 07a? 

 

Many thanks

Mike 

Replies

Zoltan Palffy
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

open Rev 8 and make rev 7 a baseline

then select maintain baselines and select update

then from here you can choose what to update all activities or a filter or additional update options under Update options 

pick and choose what to update 

when you are done select Restore to put REV7 back into the selectable projects

Mike planner
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hmnn... not that easy, because i have changed some duration and logic. 

I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another 

 

Many thanks

Mike 

Santosh Bhat
User offline. Last seen 13 weeks 6 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Don't you just make a copy of Rev 08 and then delete the new activities?