Forum Sponsor:

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 - resource is not showing activities that are completed

2 replies [Last post]
Mike planner
User offline. Last seen 13 hours 15 min ago. Offline
Joined: 3 Feb 2011
Posts: 34
Groups: None

Hello All, 

 

I suspect the resource is not showing on the activities that are completed because it is a bit light after the progress line. 

Please see image below. 

The design activities are blue resources but i cannot see anything blue on the histograme blow after that progress / data date line. 

I am suspecting the setting does not show the resources for activities that are completed but then, i can see slightly red for the construction activities which are in Red. 

I am a bit confused. 

 

Thank you for much for your help.

 

Kind regards

Mike Planner 

Replies

Zoltan Palffy
User offline. Last seen 2 days 12 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2480
Groups: None

go to view resource usage profile and make sure that on the dat tab that you have the actua box checked. 

David Kelly
User offline. Last seen 1 week 21 hours ago. Offline
Joined: 19 Oct 2004
Posts: 570

The P6 stacked histogram shows "At Completion" hours/costs - so stage 1 of your investigation is to show that value besiide the "Budgeted" numbers you have highlighted.......

Yes, "At Completion" is a bit bonkers....