Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 - resource is not showing activities that are completed

2 replies [Last post]
Mike planner
User offline. Last seen 2 years 12 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hello All, 

 

I suspect the resource is not showing on the activities that are completed because it is a bit light after the progress line. 

Please see image below. 

The design activities are blue resources but i cannot see anything blue on the histograme blow after that progress / data date line. 

I am suspecting the setting does not show the resources for activities that are completed but then, i can see slightly red for the construction activities which are in Red. 

I am a bit confused. 

 

Thank you for much for your help.

 

Kind regards

Mike Planner 

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to view resource usage profile and make sure that on the dat tab that you have the actua box checked. 

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

The P6 stacked histogram shows "At Completion" hours/costs - so stage 1 of your investigation is to show that value besiide the "Budgeted" numbers you have highlighted.......

Yes, "At Completion" is a bit bonkers....