Hello All,
I suspect the resource is not showing on the activities that are completed because it is a bit light after the progress line.
Please see image below.
The design activities are blue resources but i cannot see anything blue on the histograme blow after that progress / data date line.
I am suspecting the setting does not show the resources for activities that are completed but then, i can see slightly red for the construction activities which are in Red.
I am a bit confused.
Thank you for much for your help.
Kind regards
Mike Planner