Showing "% Complete" on Y-Axis of resource profile in P6.7

1 reply [Last post]
Sam .
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 20 Aug 2009
Posts: 15

Hi All,

 

I have searched for this answer but cannot find,

 

At the moment my resource profile (S-curve) in P6 shows time on X-axis and units on Y-axis. (Standard format)

 

What box do I tick to instead show "% complete" on the Y-axis (based on budgeted units, not actual values)

 

I have tried changing "Time Units" to "Show as Percentage" in the User Preferences, no change.

 

Many thanks

 

Sam D

Replies

Baris Hazar
User offline. Last seen 7 years 8 weeks ago. Offline
Joined: 4 Dec 2009
Posts: 39

Hi,

You can partially achieve this by dividing the resource allocation interval totals by the whole contract amount or discipline total. It depends the scope of S-Curve. (Resource Assignments-->(Right Pane) Display-->Spreadsheet Options) By doing this you will have a value between 0 and 1 on the Y axis and I think this can somehow facilitate the interpretation of S-Curve. 

Changing "Time Units" to "Show as Percentage" in the User Preferences enables you to view all the data columns titled as '.... Units/Time' in percentage wise such as the ones in Resource Dictionary or under Resources tab of Activity Details Table.

Regards,

 

baris