Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global Resource vs Project Resource

1 reply [Last post]
sharief sheikh
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 1 Mar 2008
Posts: 10
Groups: None

What is the best practice on resource assignment. Is it good to create resources for each project or use the global resource. What would be issue if we just use the global resource, please.

Replies

Santosh Bhat
User offline. Last seen 4 hours 42 min ago. Offline
Joined: 15 Apr 2005
Posts: 215

In P6 there is no such thing as Project Resources, all resources are listed in a single Global pool. Your bext option is to organise the Resources into a hierarchy that matches your EPS structure and in that respect you can create project specific reosurces by naming them.