Global change not working for baseline programme

2 replies [Last post]
Kevin Rayner
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 9 Jan 2009
Posts: 17
Groups: None

I am aware of the need to change the planned start and planned finish of a baseline programme before attaching it to the programme that I am usuing to demonstrate a delay.

However in certain instances the planned dates are not being changed. ie an activity in progress with and actual start of the 30 May 2018 and a finish of the 3 Dec 2018 after running the global change to set the planned dates gives a planned start of the 30 May 2018 but a finish of the 30 Nov 2018 and not the 3 Dec 2018.

I assume that the global change is:

Condition 1 activity complete. planned start=actual start planned finish=actual finish

Condtion 2 activity in progress. planned start=actual start planned finish=finish

Is this correct?

Replies

Kevin Rayner
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 9 Jan 2009
Posts: 17
Groups: None

You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline?

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

how come you are mixing planned start date with finish dates  ?

actual start = planned start

actual finish = planned finish