Units discrepancy for s-curve

4 replies [Last post]
Morne Johann Bees...
User offline. Last seen 33 weeks 4 days ago. Offline
Joined: 25 Feb 2016
Posts: 16
Groups: None

Loaded my permitting with units to track an s-curve. Assigned 200 000 units across the activities. My report only has 194104 units in cumulative planned but cumulative estimate to & at completion indicates the 200 000 units loaded. No filters assigned that can trip me up and percent complete type set to units.

 

What could be the problem?

 

Running 18.8

Replies

Zoltan Palffy
User offline. Last seen 3 days 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

under edit user preference

turn your decimal places on 

Time units tab

Morne Johann Bees...
User offline. Last seen 33 weeks 4 days ago. Offline
Joined: 25 Feb 2016
Posts: 16
Groups: None

Thanks David, found it is exactly the problem.

 

Going to delete resources and reload as I guess this is the only fix.

David Kelly
User offline. Last seen 2 years 47 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Primavera holds the numbers in two places, and they do get out of synchronisation.

You should check the units in both the “Activities” window and the “Resource assignment” windows

When you do a resource  profile/spreadsheet, the numbers come from one table, the Activity spreadsheet/profile and ALL earned value data comes from the other.

Zoltan Palffy
User offline. Last seen 3 days 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

make sure your filter is set to ALL activities