Hello,
The project I am working on has been bogged down during preconstruction and the Owner has directed us to add resubmittal activities for each submittal that had a revision. Unfortunately, that is more or less all of them, and the previous schedulers were not adding these activities.
Below are some challenges I am considering, and I appreciate any comments or opinions:
1) Activity Type
The Owner has requested that I add a milestone for each resubmit and a milestone for each returned submittal.
In the past I have used a task dependent activity with a duration, not a milestone. For each resubmittal iteration, I added an activity for revise & resubmit, and an activity for review & approve, until the submittal was finally approved. This created a FS fragnet without gaps.
Is it common practice or are there any benefits to using milestones instead of a fragnet of task dependent activities that have durations?
2) Re-naming the activities
The Owner has requested that I add the submittal number and response status into the submittal activity name (ie. 0105.00 Returned Not Approved).
This would create some very long activity names, especially for activities where multilpe submittal numbers constitute a single activity.
My suggestion was to include the UDFs "Submittals" and "Submittal Status" that I already include in the schedule.
Is there a reason that changing the name of an activity to include this information is preferable to using UDFs?
3) Single Submittal Package for Multilple Submittal Activities
When the Baseline was developed, individual submittal activities were added for several locations on the project. These locations each have their own WBS. However, oftentimes all of these locations are included in a single submittal package.
For example, submittal #113 might contain all shop drawings for the identical components in north, east, south, and west areas, but the schedule has individual activities and WBSs for each of these areas.
Generally, would each WBS (north, east, south, west) need a series of activities for the #113 resubmittal process, even though they have identical dates? Or, is it generally acceptable to have a single #113 series in a parent WBS and tie it to "submittal approved" milestones added to each sub-WBS area?
A single submittal package often includes up to 8 individual areas, so resolving this question is going to have a big impact on the amount of time it takes to enter all these submittal sequences. Copying and pasting works, but it is tedious to go in and change activity names to reflect the individiual location. With that many submittals, there is a lot of opportunity for error.
As always, any and all thoughts are appreciated!
GP
Replies