Progressing multiple activities

2 replies [Last post]
Floris Gering
User offline. Last seen 12 weeks 3 days ago. Offline
Joined: 30 Jul 2014
Posts: 27

What is the easiest way to progress a large number of activities in one go ?

(for example progressing all erect scaffolding work to 100% in the pre-shutdown phase of a turnaround)

I am familiar how it works to progress one activity, but manually clicking through 50 scaffolding activities is preferrably not the way to go.

Replies

Steven Auld
User offline. Last seen 7 weeks 2 days ago. Offline
Joined: 13 Sep 2017
Posts: 126

I would agree with Zoltan's last comment! It is unlikely that they were all started & completed exactly as per plan.

For only 50 activities, I would just update manually so that you can update the start & finish dates / times as required.

Depending on the size of the Turnaround & the level of detail in the plan, it is likely that you will need to update more than this most days & they will not all be the same trades so not as easy to filter.

How you capture progress during the Turnaround is critical in how long this takes to complete each day, so worth spending time getting this right before the Turnaround starts.

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can do it 2 ways 

option #1 export to excel and thne populate then import to p6

option #2

filter for all of the scaffolding activites and select 

tools Update progress then select Selected activities only

the problem that you have with doing it this way is that it assumes that all of the scaffolding in this filter started and completed on schedule (that NEVER happens)