Adding notebooks to multiple activities in P6.2

2 replies [Last post]
Eric Rivera
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 2 Jul 2008
Posts: 9
Groups: None
Guys,
I have inherited a project with about 1400 activities and none of them have notebooks attached to them. Since one of my reports keys on the presence of a notebook attached to an activity, I need to add one to each of them.
Does anyone know if there is a way to add a notebook to multiple activities at once, rather than the one-at-a-time click and confirm method?

Any help is always appreciated!

Thanks,
Eric

Replies

Eric Rivera
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 2 Jul 2008
Posts: 9
Groups: None
Thanks Muhammad! Worked like a charm!
muhammad anwar
User offline. Last seen 3 years 43 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS
Eric,

Select one activity and assign the notebook topic and before closing popup window select multiple activities by using ’CTRL’ key of keyboard and then assign the topic and it will go to all activities.

Just keep ’Assign Notebook topic’ popup window up and select the activities and hit the topic.

regards