Design Deliverable Planning

3 replies [Last post]

I have project which consists of quite a large  number of drawings.My cliet asked me to incorporate all drawings in the design and deliverables part of the project. Since i have to link all(majority of ) the drawing to construction part and each drawing will go for  two or three revisions from client how do i link to the construction part .

In short :

1. I have drawings, some of them will undergo 2 reviews,some of them will have 3 or more .

2.In this situation how do we link the drawing to the construction

Thanks and regards,

Shijau

 

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help

Thank you very much sir

 

shaiju

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

design drawings to 30%, then client review 30% drawings then 

design drawings to 60%, then client review 60% drawings then 

design drawings to IFC%, then client review IFC drawings then 

create/submit shop drawings, client review/aprrove shop drawings then

Procurement of whatever material then

install the material