Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Budgeted Units change?

1 reply [Last post]
Phil Bedford
User offline. Last seen 22 weeks 3 days ago. Offline
Joined: 23 Jun 2016
Posts: 20

This is more than likely a simple answer....

Example:

10 day activity for an electrical resource. 4 guys needed on the job for days 1-6, then drop to 2 guys for days 7 & 8 and back up to 4 for days 9 & 10.

Can this be achieved in a single activity, or do I need 3 separate activites linked F-S and up/down the resource as required?

 

Cheers,

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

you need 3 seperate activities a lot of time the scheduling specifications limits the duration for an activity to 21 days (not including long lead procurement items)